Riverside Medical Center/22 · Plumbing
22Review in progress
Plumbing
Bid package 22-100 · 3 proposals · Due Jul 22, 2:00 PM
SMAW+2Build award
7 scope items
| Canonical scopeSource-backed requirement | HCHill Country Mechanical$3,610,000 | CPCapital Plumbing Co$3,820,000 | LPLone Star Plumbing & Piping$3,940,000 |
|---|---|---|---|
22 11 16Domestic water piping14,800 LF | |||
22 13 16Sanitary waste & vent piping11,200 LF | |||
22 40 00Plumbing fixtures214 EA | |||
22 33 00Electric water heaters6 EA | |||
22 07 19Piping insulation9,400 LF | |||
22 05 73Underground utilities & excavationUnderground | |||
01 74 19.01Progress cleanup and final cleanGeneral requirements |
Bid summaryOnly approved adjustments affect qualified totals and rank
Original bid $3,610,000
Approved in total: $48,000
Open exposure +$245,000Original bid $3,820,000
Approved in total: $36,000
Open exposure +$42,000Original bid $3,940,000
Approved in total: $22,000
Open exposure +$18,000Loading bid depth…