Bid package 22-100 · 3 proposals · Due Jul 23, 2:00 PM

3 scope gaps open
Open scope gaps3
Scope-gap exposure$659,000
Scope-gap exposure resolved$0
criticalHill Country Mechanical

Rock excavation excluded

Hill Country excludes rock excavation for the underground utilities despite Geotech GR-02 noting a limestone shelf at 4'-6".

Est. exposure$392,000Working exposure
mediumLone Star Plumbing & Piping

Sanitary waste only partial

Lone Star carries above-grade sanitary only; below-slab collection to the building line is omitted.

Est. exposure$180,000Working exposure
mediumCapital Plumbing Co

Water heaters silent

Capital Plumbing is silent on the 6 electric water heaters scheduled at the mechanical rooms.