Direct cost
$24M
Labor + material + subcontract + equipment
Riverview Medical Office · Direct cost, general conditions, fee, and contingency computed live from cost-coded budget lines
Not in the grand total: General conditions $685,000 · General requirements $215,000. These budget lines are superseded by the rate-derived general conditions and fee above, which the total uses instead. Shown so nothing is hidden, not added twice.
Every line shows where the number came from — takeoff, award, manual entry, or an approved change order
| Cost code | Description | Kind | Qty | Source | Amount |
|---|---|---|---|---|---|
| 01 10 00 · Project management & field supervision | $900,000 | ||||
| 01 10 00 | Field supervision & general conditions staff (13-month duration) | General conditions | — | Manual | $685,000 |
| 01 10 00 | Temporary facilities, progress cleaning & permits | General requirements | — | Manual | $215,000 |
| 03 30 00 · Slab & foundations | $2,900,000 | ||||
| 03 30 00 | Slab & foundations (awarded: Cornerstone Concrete Co.) | Subcontract | — | Award | $2,900,000 |
| 04 20 00 · Exterior masonry | $1,180,000 | ||||
| 04 20 00 | Exterior masonry (awarded: Lone Star Masonry) | Subcontract | — | Award | $1,180,000 |
| 05 12 00 · Steel frame & erection | $2,760,000 | ||||
| 05 12 00 | Steel frame & erection (awarded: Capitol Steel Erectors) | Subcontract | — | Award | $2,760,000 |
| 07 50 00 · Roofing & waterproofing | $1,940,000 | ||||
| 07 50 00 | Roofing & waterproofing (awarded: Summit Roofing) | Subcontract | — | Award | $1,940,000 |
| 08 10 00 · Door & hardware package | $2,140,000 | ||||
| 08 10 00 | Door & hardware package | Subcontract | — | Award | $2,140,000 |
| 09 10 00 · Interior finishes | $1,370,000 | ||||
| 09 10 00 | Interior finishes (Apex Interiors, qualified low bid) | Subcontract | — | Award | $1,370,000 |
| 09 22 16 · Wall protection backing — framing | $76,638 | ||||
| 09 22 16 | Wall protection backing framing — labor (GC self-perform) | Labor | 4,820 LF | Takeoff | $45,790 |
| 09 22 16 | Wall protection backing framing — material (GC self-perform) | Material | 4,820 LF | Takeoff | $30,848 |
| 21 10 00 · Fire sprinkler | $612,000 | ||||
| 21 10 00 | Fire sprinkler (awarded: Guardian Fire Protection) | Subcontract | — | Award | $612,000 |
| 22 10 00 · Plumbing | $3,820,000 | ||||
| 22 10 00 | Plumbing | Subcontract | — | Award | $3,820,000 |
| 23 10 00 · HVAC | $2,900,000 | ||||
| 23 10 00 | HVAC (awarded: Central Mechanical) | Subcontract | — | Award | $2,900,000 |
| 26 10 00 · Electrical | $4,650,000 | ||||
| 26 10 00 | Electrical | Subcontract | — | Award | $4,650,000 |
| Estimate-level (no cost code) | $480,000 | ||||
| — | Design contingency — owner-held scope maturity reserve | Contingency | — | Manual | $480,000 |